Energy

Nuon MK10 relocation – Energy market

SCOPE

Relocation of MK10 Nuon power station (100 MW) from Utrecht to foreign destination; Tacon was responsible for decommissioning, dismantling and transport to the port of Rotterdam

  • Feasibility study
  • Engineering & Procurement
  • Management and Coordination of contractors
  • Decommissioning
  • Disassembly & transport
  • Remediation ‘existing’ location

SCOPE

  • Tacon team of about six specialists
  • Ca. 18 months lead time
  • Management and Coordination of about 20 contractors
  • Overall project budget around 7 M €

Central Claus C Maasbracht

SCOPE

Tacon was responsible for management, preparation and construction of the greenfield gas-fired power plant (1300 MW), bring up and running, on-site security assistance (eg., Gatekeeping, spell registration).

  • Tacon management and construction team of 20 employees
  • Start preparing in June 2008, original delivery date July 31, 2011 (first start).
  • Ca. 4M executive Hours
  • Average of 3,500 jobs
  • Budgeted 1,050 M €

Results

0 security incidents initial start approximately 3 months earlier and within budget.